Themis Hop Test Hangs on November Decision Amid Winter
ESA will decide by late November if winter conditions at Sweden's Esrange Space Center will allow the first Themis reusable rocket hop test to occur before year-end, jeopardizing a 2027 deadline.

The European Space Agency must decide by the end of November 2026 whether the Themis reusable rocket demonstrator can attempt its first flight before winter shuts down Sweden's Esrange Space Center. ESA Director of Space Transportation Géraldine Naja stated on 22 October that she was uncertain the first flight would occur before the end of 2026, citing approaching winter conditions.
Winter conditions threaten first hop test
Winter weather in northern Sweden risks postponing the inaugural hop test of the 30-metre-tall Themis T1H vehicle this year. The compressed schedule to complete two flights adds to existing technical risks, which include cryogenic fuelling, engine testing, and executing an autonomous landing. The next decision point is due by the end of November 2026, when officials will make a go/no-go decision on attempting the flight before the seasonal shutdown.
Program budget and scope under EU SALTO
The initial two-hop flight campaign is conducted under the European Commission's SALTO initiative. This program aims to complete two low-altitude hop tests to prove the Themis stage can be launched, recovered, and reflown. The project has a total budget of €42.8 million.
| Item | Figure |
|---|---|
| Total SALTO Project Cost | €42.81 million |
| EU Contribution | €39 million |
| EU Share of Funding | 91.1% |
| Non-EU Costs | €3.81 million |
This funding covers technology development and testing, not a per-flight cost. The Commission's CORDIS database lists the SALTO project end date as 31 December 2026, while Naja indicated the development schedule required a hop test to occur before June 2027. An ESA spokesperson did not clarify whether the June 2027 deadline applied to both tests, reiterating that the November decision pertained only to the first hop.
Technical preparations and safety rehearsals
Extensive ground rehearsals have been conducted to prepare for the flight. A rehearsal on 29 September 2026 used liquid nitrogen, cooled to roughly -200°C, instead of methane and oxygen for safety. These tests validated cold tank procedures, countdown sequences, and automated ground handling. ESA commented on that rehearsal on 7 October 2026.
Ground handling plans involve robots locating the landed vehicle, connecting drainage lines, and removing residual fuel and oxidizer before crew approach for maintenance. The preparation sequence also includes a planned hot-fire test where the Prometheus engine will run while the stage is restrained after propellant loading. For the first hop, the engine will stay running throughout the flight to an altitude of up to 100 metres, targeting a 20m x 20m landing area. Engine shutdown and restart are reserved for a later, higher-altitude campaign.
Prior to Naja's October statement, no official updates had specified a revised flight date. ArianeGroup's 7 October update, following a successful second wet dress rehearsal, noted teams were defining a window for the next test. A go/no-go decision on proceeding with the flight before winter shutdown will be made by the end of November 2026.